Question: A partial information about a project is shown below. Activities G and T must be completed before activity C can start. Activities G, T, and

A partial information about a project is shown
A partial information about a project is shown below. Activities G and T must be completed before activity C can start. Activities G, T, and N must be completed before activity M can start Activities C and M must be completed before activity D can start Activity M must be complete before activity A can start. The duration of activities G, T, N are 19, 16, and 24 days, respectively. . The duration of activities C, M are 45, and 38 days, respectively. Furthermore ES(G) = 16, ES(T) = 17. and ES(N) = 25. Find the value of ES(D)