Question: A partial information about a project is shown below. Activity K 28 days, IP = F G Activity M, 31 days, IP = F G

A partial information about a project is shown
A partial information about a project is shown below. Activity K 28 days, IP = F G Activity M, 31 days, IP = F G H Activity N 44 days, IP = G, H Activity P 35 days IP = K Activity Q: 39 days, IP = K M N It has been calculated that EF(F) = 17 EF(G) = 19 and EF(H) = 20 Find the value of EF(Q)