Question: A partial information about a project is shown below. Activity K; 39 days; IP = F, G Activity M; 42 days; IP = F, G,

A partial information about a project is shown below.

Activity K; 39 days; IP = F, G Activity M; 42 days; IP = F, G, H Activity N; 37 days; IP = G, H Activity P; 21 days; IP = K Activity Q; 34 days; IP = K, M, N It has been calculated that EF(F) = 22, EF(G) = 22 , and EF(H) = 31.

Find the value of EF(Q).

A partial information about a project is shown
15 pts Question 9 A partial information about a project is shown below. Activity K; 39 days; IP = F, G Activity M; 42 days; IP = F, G, H Activity N; 37 days; IP = G, H Activity P; 21 days; IP = K Activity Q; 34 days; IP = K, M, N It has been calculated that EF(F) = 22, EF(G) = 22, and EF(H) = 31. Find the value of EF(Q)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!