Question: A partially complete MRP release schedule for a part with a lead time of 1 week and a batch size of 60 is below. When
A partially complete MRP release schedule for a part with a lead time of 1 week and a batch size of 60 is below. When and how large of planned order release should be placed to meet the week 4 requirement?
| Week 0 | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 |
| |||||||
| Gross requirements | 0 | 0 | 0 | 170 | 0 |
| |||||||
| On Hand Inventory | 30 | 30 | 30 | 30 | 30 |
| |||||||
| NET POQ Req | 0 | 0 |
|
|
|
| |||||||
| Planned receipts | 0 | 0 |
|
|
|
| |||||||
| Planned orders |
|
|
|
|
|
| |||||||
|
| a. | b. | c. | d. | e. | f. | |||||||
|
| Week 1, 180 | Week 1,140 | Week 2, 140 | Week 2, 180 | Week 3, 140 | Week 3, 180 | |||||||