Question: A partially complete MRP release schedule for a part with a lead time of 1 week and a batch size of 60 is below. When

A partially complete MRP release schedule for a part with a lead time of 1 week and a batch size of 60 is below. When and how large of planned order release should be placed to meet the week 4 requirement?

Week 0

Week 1

Week 2

Week 3

Week 4

Week 5

Gross requirements

0

0

0

170

0

On Hand Inventory

30

30

30

30

30

NET POQ Req

0

0

Planned receipts

0

0

Planned orders

a.

b.

c.

d.

e.

f.

Week 1, 180

Week 1,140

Week 2, 140

Week 2, 180

Week 3, 140

Week 3, 180