Question: A partially solved PERT problem is detailed in the table below. Times are given in weeks. Optimistic Probable Pessimistic Expected Activity Preceding Time Time Time

A partially solved PERT problem is detailed in the table below. Times are given in weeks. Optimistic Probable Pessimistic Expected Activity Preceding Time Time Time Time Variance A 7 9 14 1.361 B A 2 2 8 0 A 8 12 16 0 A 3 5 10 1.361 B 4 6 8 0 B 6 CO 10 O C, F 2 4 0 H D 2 H CO N9 8 1.000 16 2.778 G. I 6 14 2.778 K E, J 5 0.250 a. Calculate the expected time for each activity. Enter these values in the appropriate column in the table above. b. Which activities form the critical path? c. What is the estimated time of the critical path? d. What are the project variance and the project standard deviation? e. What is the probability of completion of the project after week 40
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
