Question: A partially solved PERT problem is detailed in the table below Times are given in weeks Optimistic Probable Pessimistic Expected Activity Preceding Time Time Time

A partially solved PERT problem is detailed in

A partially solved PERT problem is detailed in the table below Times are given in weeks Optimistic Probable Pessimistic Expected Activity Preceding Time Time Time Time Varance A 7 10 19 B A 2 2 8 A 8 12 16 D A 3 5 10 E B 4 6 8 F B 6 8 10 G CF 2 3 4 H D 2 2 8 ! H 6 8 16 J G1 4 6 14 K EJ 2 5 8 > (a) Calculate the expected time and variance for each activity Enter these values in the appropriate columns in the table above (b) Which activities form the critical path? (c) What is the estimated time of the critical path? (d) What are the project variance and the project standard deviation? (e) What is the probability of completion of the project before week 427

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!