Question: A particular process is analyzed and an appropriate value stream map (VSM) is created. The total non-value added time is estimated at 10,900 seconds, and
A particular process is analyzed and an appropriate value stream map (VSM) is created. The total non-value added time is estimated at 10,900 seconds, and the total value-added time is approximately 595 seconds. The rolled throughput yield (RTY) is 93.6%. What is the productive ratio?