Question: A particular process is analyzed and an appropriate value stream map (VSM) is created. The total non-value added time is estimated at 10,900 seconds, and
A particular process is analyzed and an appropriate value stream map (VSM) is created. The total non-value added time is estimated at 10,900 seconds, and the total value-added time is approximately 595 seconds. The rolled throughput yield (RTY) is 93.6%. What is the productive ratio?
a. 5.18%
b. 4.84%
c. 5.46%
d. 6.40%
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
