Question: A perfectly controlled project that ended exactly as predicted would have both the Cost Variance and Schedule Variance in Time equal to zero. Review Later

A perfectly controlled project that ended exactly as predicted would have both the Cost Variance and Schedule Variance in Time equal to zero.
Review Later
True
 
False This question says its false but the explanation directs you to being it True so it's confusing. Please explain?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

You are correct In a perfectly controlled project both the Cost Variance ... View full answer