Question: A perfectly controlled project that ended exactly as predicted would have both the Cost Variance and Schedule Variance in Time equal to zero. Review Later
Step by Step Solution
There are 3 Steps involved in it
You are correct In a perfectly controlled project both the Cost Variance ... View full answer