Question: A perfectly controlled project that ended exactly as predicted would have both the Cost Variance and Schedule Variance in Time equal to zero. True False
A perfectly controlled project that ended exactly as predicted would have both the Cost Variance and Schedule Variance in Time equal to zero.
True
False