Question: A PERT / CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 1 4 days, and a pessimistic
A PERTCPM activity has an optimistic time estimate of days, a most likely time estimate of days, and a pessimistic time estimate of days. What is the expected time in days of this activity? Round your answer to two decimal places.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
