Question: A PERT / CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 1 4 days, and a pessimistic

A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 14 days, and a pessimistic time estimate of 26 days. What is the expected time (in days) of this activity? Round your answer to two (2) decimal places.
 A PERT/CPM activity has an optimistic time estimate of 3 days,

Step by Step Solution

There are 3 Steps involved in it