Question: Project Management BUS 344 - 423 - Practice Problems 1) An activity has an optimistic time estimate of 17 days, a most likely estimate of

Project Management BUS 344 - 423 - Practice
Project Management BUS 344 - 423 - Practice Problems 1) An activity has an optimistic time estimate of 17 days, a most likely estimate of 23 days, and a pessimistic estimate of 37 days. What is the variance of the activity