Question: A planner receives a request from a customer for a change in the Master Production Schedule. This change falls with the cumulative lead time. Which

A planner receives a request from a customer for a change in the Master Production Schedule. This change falls with the cumulative lead time. Which of the following techniques would the planner use to respond to this request?
Multiple Choice
Product explosions.
Time phasing.
What if.
Time fencing.