Question: A process has a lower specification limit and no upper limit. The current process yield has 0.39% of everything below the lower limit. What is
A process has a lower specification limit and no upper limit. The current process yield has 0.39% of everything below the lower limit. What is the capability (Cpk) of this process.
Question 2 options:
|
| 2.66 |
|
| 0.89 |
|
| 2.84 |
|
| 1.67 |