Question: A process has been sampled and it is found to have a Cpk on the upper side of 2.4 and a Cpk on the lower

A process has been sampled and it is found to have a Cpk on the upper side of 2.4 and a Cpk on the lower side of 1.4. The Cp for this process would be: a. 2 b. 1.9 c. 3.8 d. 4.8 e. The value of the pr