Question: A process has C_(p)=1.2 and C_(pk)=0.9 . Based on this, what do we know to be true? Select one: a. The process has the potential
A process has C_(p)=1.2 and C_(pk)=0.9 . Based on this, what do we know to be true? Select one: a. The process has the potential to meet specifications, but is currently too far off-center. b. The pro