Question: A process has three activities connected in series. The first activity ( A ) has a cycle time of 5 minutes and a lead time

A process has three activities connected in series. The first activity (A) has a cycle time of 5 minutes and a lead time of 5 minutes, the second activity (B) has a cycle time of 2 minutes and a lead time of 10 minutes, the third activity (C) has a cycle time of 1minutes and a lead time of 5 minutes. Each activity is currently manned by 1person. The process works for 8 hours in a day and the demand is 120 per day. How many people should be sufficient for these activities?
1 point
1
2
3
4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!