Question: A process has three activities connected in series. The first activity ( A ) has a cycle time of 5 minutes, the second activity (
A process has three activities connected in series. The first activity A has a cycle time of minutes, the second activity B has a cycle time of minutes, the third activity C has a cycle time of minutes. Each activity is currently manned by person. The process works for hours in a day and the demand is per day. Which activity is the bottleneck in the process?
point
A
B
C
None of the above