Question: A process has three activities connected in series. The first activity ( A ) has a cycle time of 5 minutes, the second activity (

A process has three activities connected in series. The first activity (A) has a cycle time of 5 minutes, the second activity (B) has a cycle time of 2 minutes, the third activity (C) has a cycle time of 1minutes. Each activity is currently manned by 1 person. The process works for 8 hours in a day and the demand is 120 per day. Which activity is the bottleneck in the process?
1 point
A
B
C
None of the above