Question: A process has two subsequent stages with the following information: 1) Stage 1 has 4 processors, and each processor has a capacity of 9 units
A process has two subsequent stages with the following information:
1) Stage 1 has 4 processors, and each processor has a capacity of 9 units per hour
2) Stage 2 has 5 processors, and each processor has a capacity of 7 units per hour
Which of these two stages is the bottleneck?
Group of answer choices
Stage 1
Can be neither, depending on the demand
Can be either, depending on the demand
Stage 2