Question: A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and each worker must be assigned
A process includes 9 tasks and there are 3 workers. Each task can be assigned to only one worker and each worker must be assigned consecutive tasks.The time to complete tasks 1 to 9 (in seconds) are as follows:
90, 75, 25, 25, 50, 30, 10, 80, 90
What is the capacity of this process in units per hour?
Note: Round your answer to 1 decimal place.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock