Question: A process includes 9 tasks and there are 3 workers Each task can be assigned to only one worker and each worker must be assigned

A process includes 9 tasks and there are 3
A process includes 9 tasks and there are 3 workers Each task can be assigned to only one worker and each worker must be assigned consecutive tasks. The time to complete tasks 1 to 9 in seconds) are as follows 50,65,15,15,35,25 45,90,90 Instruction Round your answer to one decimal place What is the capacity of this process in units per hout? Units per hour