Question: A process includes four steps (as shown below). A separate person works at each of the steps and they use a 8 hour work day
A process includes four steps (as shown below). A separate person works at each of the steps and they use a 8 hour work day shift.
>> Step 1 >> Step 2 >> Step 3 >> Step 4 >>
Step 1 takes 2 min per order Step 2 takes 4 min per order Step 3 takes 1 min per order Step 4 takes 3 min per order What is the current maximum output of the whole process per day?
| 60 | ||
| 80 | ||
| 120 | ||
| 240 | ||
| None of the above |