Question: A process includes four steps ( as shown below ) . A separate person works at each of the steps and they use a 7

A process includes four steps (as shown below). A separate person works at each of the steps and they use a 7 hour work day shift."Step 1" takes 3 min per order
"Step 2" takes 7 min per order
"Step 3" takes 5 min per order
"Step 4" takes 2 min per order
What is the current maximum output of the whole process per day?
60
84
140
210
None of the above