Question: A process is scheduled to run 2 4 hours every weekday across 3 shifts. Each shift gets a 2 0 - minute break. There is
A process is scheduled to run hours every weekday across shifts. Each shift gets a minute break. There is also a minute production meeting at the start of each shift. The total operation time for part is minute.
Hint: all times must be converted to seconds first
The demand for the product is parts per week.
a Determine the TAKT time for the process and explain briefly what this means.
b Determine the number of workers required in this process.