Question: A process makes two products, A and B and operates 5 days per week, 8 hours per day. Demand for the two products for the

 A process makes two products, A and B and operates 5

A process makes two products, A and B and operates 5 days per week, 8 hours per day. Demand for the two products for the next week is as follows: Day 1: A: 20 B: 26 Day 2: A: 10 B: 15 Day 3: A: 20 B: 19 Day 4: A: 18 B: 20 Day 5: A: 12 B: 20 a. What is the takt time of the process? Note: Round your answer to 5 decimal places. b. What would a level production schedule look like? ABABABABB ABABABABB ABABABABA ABABABABA BABABABAB ABABABABA ABABABABA BABABABAB