Question: A process makes two products, A and B and operates 5 days per week, 8 hours per day. Demand for the two products for the

A process makes two products, A and B and

A process makes two products, A and B and operates 5 days per week, 8 hours per day. Demand for the two products for the next week is as follow: Day 1: : 20 : 26 Day 2: : 10 : 15 Day 3: : 20 : 19 Day 4: : 18 : 20 Day 5: : 12 : 20 (Round your answer to 5 decimal place.) What is the takt time of the process? hours/unit What would a level production schedule look like? CABABABABB ABABABABB ABABABABA ABABABABA OBABABABAB ABABABABA ABABABABA BABABABAB