Question: A process to produce a product has five sequential steps, A B C D E . The throughput rates, in lbs / hour ( of

A process to produce a product has five sequential steps, ABCDE. The throughput rates, in lbs/hour (of product) for the steps are 50,40,120,90, and 70 for steps A,B,C,D, and E, respectively. What is the maximum system output of product in lbs per hour?
 A process to produce a product has five sequential steps, ABCDE.