Question: A product design engineer must decide if a redundant component is cost-justified in a certain system. The system in question has a critical component with
A product design engineer must decide if a redundant component is cost-justified in a certain system. The system in question has a critical component with a probability of 0.96 of operating. System failure would involve a cost of GHS40,000. For a cost of GHS1000, a switch could be added that would automatically transfer the system to the backup component in the event of a failure. What is the expected cost of failure if a backup is not added?
Given this information, the expected cost of failure if a backup with reliability of 0.96 is added is GHS