Question: A product design engineer must decide if a redundant component is cost-justified in a certain system. The system in question has a critical component with
A product design engineer must decide if a redundant component is cost-justified in a certain system. The system in question has a critical component with a probability of 0.98 of operating. System failure would involve a cost of GHS20,000. For a cost of GHS100, a switch could be added that would automatically transfer the system to the backup component in the event of a failure.
Given this information, the expected cost of failure if a backup is not added is GHS
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
