Question: A product design project is broken down into 1 0 activities, as listed in the following table. Activity Predecessor Time ( Weeks ) A -

A product design project is broken down into 10 activities, as listed in the following table.
Activity Predecessor Time (Weeks)
A --4
B --2
C A 4
D A 3
E B, C 5
F C 6
G D 2
H E 3
I F, G 7
J H 7
a) Draw a Gantt chart for the project, assuming each activity starts as early as possible.
b) Draw the activity-on-node (precedence diagram) of the project.
c) Compute the earliest start, earliest finish, latest start, latest finish, and slack times of the activities using the critical path method.
d) What is the project duration?
e) Which activities are critical?
f) What is(are) the critical paths of the project?
g) Suppose all activities except A and C can be shortened by 1 week each. The crash cost is
$5,000 per week per activity.
Which activities would you shorten to reduce the project duration by 3 weeks?
In which sequence should these activities be shortened?
How much crashing cost will be incurred to reduce the project duration by 3 weeks? What is(are) the critical path(s) of the project after crashing?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!