Question: A product design project is broken down into 1 0 activities, as listed in the following table. Activity Predecessor Time ( Weeks ) A -
A product design project is broken down into activities, as listed in the following table.
Activity Predecessor Time Weeks
A
B
C A
D A
E B C
F C
G D
H E
I F G
J H
a Draw a Gantt chart for the project, assuming each activity starts as early as possible.
b Draw the activityonnode precedence diagram of the project.
c Compute the earliest start, earliest finish, latest start, latest finish, and slack times of the activities using the critical path method.
d What is the project duration?
e Which activities are critical?
f What isare the critical paths of the project?
g Suppose all activities except A and C can be shortened by week each. The crash cost is
$ per week per activity.
Which activities would you shorten to reduce the project duration by weeks?
In which sequence should these activities be shortened?
How much crashing cost will be incurred to reduce the project duration by weeks? What isare the critical paths of the project after crashing?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock