Question: A production facility includes a workstations, WS1, WS2 and WS3, connected in series. Because of excessive scrap in workstation 1 and 2, two additional rework

A production facility includes a workstations,

A production facility includes a workstations, WS1, WS2 and WS3, connected in series. Because of excessive scrap in workstation 1 and 2, two additional rework stations (RW1 and RW2) are added to production line to reclaim some of the rejects coming from the workstations? How many units must the process start with in order to meet the required output (O) of 10,000 units? d1 d3 drw1 0,20 d2 0,10 drw! 0,20 0,20 0,09 drw2 RW2 d2 WS1 WS2 WS3 d1 d3 RW1 drw 1