Question: A production line has two workstations and a 100-second required cycle time. The total amount of actual task time across all workstations is 180 seconds.
A production line has two workstations and a 100-second required cycle time. The total amount of actual task time across all workstations is 180 seconds. What is the total idle time? Group of answer choices A. 10 seconds. B. 20 seconds. C. 40 seconds. D. 80 seconds.