Question: A production line has four workstations and a 50- second cycle time. The total amount of actual task time across all four workstations is 170

A production line has four workstations and a 50- second cycle time. The total amount of actual task time across all four workstations is 170 seconds. What is the idle time? The percent idle time? The efficiency delay?