Question: A production line has two workstations and a 70-second cycle time. The total amount of actual task time across all two workstations is 110 seconds.
A production line has two workstations and a 70-second cycle time. The total amount of actual task time across all two workstations is 110 seconds.
Part 2
The idle time is
enter your response here
seconds. (Enter your response as a whole number.)
Part 3
The percent idle time is
enter your response here%.
(Enter your response rounded to one decimal place.)
Part 4
The efficiency delay is
enter your response here%.
(Enter your response rounded to one decimal place.)