Question: A production process has three workstations. The first workstation has a capacity of 125 units per hour, the second workstation has a capacity of 115
A production process has three workstations. The first workstation has a capacity of 125 units per hour, the second workstation has a capacity of 115 units per hour, and the third workstation has a capacity of 140 units per hour. Demand for the process is 180 units per hour. What is the utilization of the first workstation in a push process? A production process has three workstations. The first workstation has a capacity of 125 units per hour, the second workstation has a capacity of 115 units per hour, and the third workstation has a capacity of 140 units per hour. Demand for the process is 180 units per hour. What is the utilization of the first workstation in a push process? 100% 63.9% 77.8% 92.0%