Question: Q8.2 (Algo) Push [8.4] A production process has two machines. The first machine has a capacity of 150 units per hour and the second machine

Q8.2 (Algo) Push [8.4]

A production process has two machines. The first machine has a capacity of 150 units per hour and the second machine has a capacity of 30 units per hour. Demand for the process is 100 units per hour.

(a) In a push process, what would be the utilization of the first machine?

(b) How would the situation change with a pull system?