Question: A program is divided into 3 blocks that are being compiled on 3 parallel computers. Each block takes an Exponential amount of time, 5 minutes
A program is divided into 3 blocks that are being compiled on 3 parallel computers. Each block takes an Exponential amount of time, 5 minutes on the average, independently of other blocks. The program is completed when all the blocks are compiled. Compute the expected time it takes the program to be compiled.