Question: A program manager elects not to bid on a proposal since the probability of winning the job is low and it requires significant investment to
A program manager elects not to bid on a proposal since the probability of winning the job is low and it requires significant investment to participate in the proposal effort. This type of approach is known as: a. Risk Mitigation Planning b. Risk Avoidance Strategy c. Risk Reduction Strategy d. Risk Transfer Strategy e. Risk Acceptance Strategy