Question: A project activity requires 12 hours most likely time; however, it is also stated that the optimal activity time is 10 hours and pessimist time

A project activity requires 12 hours most likely time; however, it is also stated that the optimal activity time is 10 hours and pessimist time to complete the activity is 26 hours.

What is the weighted estimated time used in the PERT algorithm?