Question: A project being analyzed by PERT has 60? activities, 13 of which are on the critical path. If the estimated time along the critical path
A project being analyzed by PERT has 60? activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of? 100, what is the pr