Question: The main difference between PERT and CPM is that Group of answer choices PERT is more accurate than CPM PERT assumes that activity durations are
The main difference between PERT and CPM is that
Group of answer choices
PERT is more accurate than CPM
PERT assumes that activity durations are known
CPM assumes that activity durations can vary
None
A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, the probability that the project will take 234 days or more to complete is
0.02275
0.97725
0
0.1587
0.8413
An activity on a PERT network has these time estimates: optimistic = 2, most likely = 5, and pessimistic = 11. Its expected time is
Group of answer choices
5
5.33
5.5
18
None