Question: A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path

A project being analyzed by PERT has 60
A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 81 , what is the probability that the project will take 218 days or more to complete? Choose the closest number. 0.0126 0.8413 0.6716 0.1587 0.3283