Question: A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path
A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, what is the probability that the project will take LESS THAN 224 days to complete?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
