Question: A project being analyzed by PERT has one critical path with 3 activities, with expected duration of 17, 25, 30, and variance of 6, 8,
A project being analyzed by PERT has one critical path with 3 activities, with expected duration of 17, 25, 30, and variance of 6, 8, 11, respectively. If the project is only given 74 days, what is the probability that the project will NOT meet the deadline? A. 0.3446 B. 0.4681 C. 0.5319 D. 0.6554