Question: A project budget calls for the following expenditures: Task Date Budgeted Amount Build Forms April 1 $ 1 0 , 0 0 0 Pour Foundation

A project budget calls for the following expenditures:
Task Date Budgeted Amount
Build Forms April 1 $10,000
Pour Foundation April 1 $50,000
May 1 $100,000
Frame Walls May 1 $30,000
June 1 $30,000
Remaining Tasks July 1 and Beyond $500,000
Complete an earned-value analysis by calculating BAC, PV, EV, SV, CV, SPI, CPI, ETC, and EAC. AC is $160,000. The cost variance is typical.