Question: A project can close as planned or be terminated early, In either event, closing activities include securing customer feedback and approval, planning and conducting a

A project can close as planned or be terminated early, In either event, closing activities include securing customer feedback and approval, planning and conducting a smooth transition of project deliverable to a credit or into ongoing operations. What key input is required before a project or project phase can move to the closing stage?

a. Acceptable deliverables

b. Work performance Reviews

c. Updated issues log

d. Changes requests