Question: A project can close as planned or be terminated early. In either event, closing activities include securing customer feedback and approval, planning and conducting a
A project can close as planned or be terminated early. In either event, closing activities include securing customer feedback and approval, planning and conducting a smooth transition of project deliverables to a client or into ongoing operations. What key input is required before a project or project phasacr move to the closing stage?
A Updated Issues Log
B Accepted deliverables
C Change Requests
D Work Pelformance Reviews