A project consists of 7 activities A.....G with the following predecessor activities, expected times and variances:...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
A project consists of 7 activities A.....G with the following predecessor activities, expected times and variances: Activity A B C D E F G Immediate Predecessor Ii = Yi = A,B B A,C C,D E,F Expected Time in Days Variance 7 0.30 5 7 8 6 0.35 0.43 0.25 1.00 0.41 0.68 (a) Activity E has an optimistic time of 4 days, a most probable time of 7 days and a pessimistic time of 10 days. How can the expected time of 7 days and the variance of = 1 be computed from these optimistic, most probable and pessimistic times? (b) Draw a project network. (c) Prepare an activity schedule, i.e. determine earliest and latest start and finish times. (d) What are the critical activities and what is the expected project completion time? (e) What is the variance of the expected project completion time? (f) Find the probability that the project will be completed in 29 or fewer days. HINT: Use the provided table for the standard normal distribution in file Area_for_the_Standard Normal Distribut (g) Formulate a linear programming model for crashing times for this project, do not solve it! As decision variables use. the earliest finish time for activity i the amount of time activity i is crashed. Parameters are the maximal crashing times M₁, the costs ki to speed up activity i by one day and the new completion time Tnew = 25 days. A project consists of 7 activities A.....G with the following predecessor activities, expected times and variances: Activity A B C D E F G Immediate Predecessor Ii = Yi = A,B B A,C C,D E,F Expected Time in Days Variance 7 0.30 5 7 8 6 0.35 0.43 0.25 1.00 0.41 0.68 (a) Activity E has an optimistic time of 4 days, a most probable time of 7 days and a pessimistic time of 10 days. How can the expected time of 7 days and the variance of = 1 be computed from these optimistic, most probable and pessimistic times? (b) Draw a project network. (c) Prepare an activity schedule, i.e. determine earliest and latest start and finish times. (d) What are the critical activities and what is the expected project completion time? (e) What is the variance of the expected project completion time? (f) Find the probability that the project will be completed in 29 or fewer days. HINT: Use the provided table for the standard normal distribution in file Area_for_the_Standard Normal Distribut (g) Formulate a linear programming model for crashing times for this project, do not solve it! As decision variables use. the earliest finish time for activity i the amount of time activity i is crashed. Parameters are the maximal crashing times M₁, the costs ki to speed up activity i by one day and the new completion time Tnew = 25 days.
Expert Answer:
Answer rating: 100% (QA)
a To compute the expected time and variance from the optimistic most probable and pessimistic times you can use the PERT Program Evaluation and Review ... View the full answer
Related Book For
Posted Date:
Students also viewed these general management questions
-
Find the probability that the claim will be rejected assuming that the manufacturers claim is true. A drug manufacturer claims that a drug cures a rare skin disease 75% of the time. The claim is...
-
Find the probability that the claim will be accepted assuming that the actual probability that the drug cures the skin disease is 65%. A drug manufacturer claims that a drug cures a rare skin disease...
-
What are the critical assumptions that Microsoft is making in buying Nokia? Do you believe these assumptions are realistic? Explain your answer.
-
Subsequent Events and Subsequently Discovered Facts. Michael Ewing is auditing the financial statements of Dallas Company for the year ended December 31, 2014. In concluding the process of gathering...
-
Not all the items in your office supply store are evenly distributed as far as demand is concerned, so you decide to forecast demand to help plan your stock. Past data for legal-sized yellow tablets...
-
Look up the annual reports for Ford and GM who trade stock in a public stock exchange such as the NYSE. Evaluate each company's profitability (pg 414), compare the two, and come up with a value...
-
In the spectrometer shown in Figure P24.67, do the ions have positive or negative charge? A. Positive B. Negative. If you have a sample of unknown composition, a first step at analysis might be a...
-
Sapporo K.K. was sued by a competitor in late 2017, and company management concluded that there was a 55 percent probability that the company would lose the lawsuit. The best estimate of the loss on...
-
Discuss four ways to improve group decision-making. Which one do you think is best? Why? Give an example of how it might be used in a police department. Discuss the advantages and disadvantages of...
-
Chelsea Bush is an emerging candidate for her partys nomination for President of the United States. She now is considering whether to run in the high-stakes Super Tuesday primaries. If she enters the...
-
choose a multiple-access protocol that provides the best performance for the following scenarios. Please consider the following protocols: TDMA, FDMA, CSMA/CD, CSMA/CA, Token-passing, and polling...
-
Deposits by buyer forfeited in 2020 Incidental costs On Acquisition On Disposal Selling price Required: RM10,000 RM24,000 RM50,000 RM40,000 RM 6,000 RM10,000 RM15,000 RM280,000 RM330,000 RM355,000...
-
The liquid phase reaction given below A+B2C is carried out adiabatically in a CSTR. A and B are fed to the reactor at 200C together with a diluent (with a molar ratio of A:B:D=1:1:3 ). Calculate the...
-
An investor purchases a stock for $50 and a put for $0.50 with a strike price of $46. The investor sells a call for $0.50 with a strike price of $59. What is the maximum profit and loss for this...
-
The partnership starting up and the old one is dissolved. Does that also mean you have to close the books and post to the capital accounts or can you continue to the normal year end and close the...
-
Compare and contrast two popular Case Management Software for Canadian Immigration.
-
1) Suppose you are given the following information: Years: 27 Present Value: $550,000 Future Value: $4,000,000 Calculate the interest rate required on the investment. (Enter percentages as decimals...
-
Determine the reactions in supports A and D and connections B and C. Sketch its shear and moment diagram and determine the magnitude ankoration of the maximum shear and moment for every member. 18 3...
-
Solve the linear programming model formulation in Problem 21 for London Fashions graphically. a. Determine the sensitivity ranges for the cost of TV. b. Does the company give any more print media ads...
-
Two coffee house chains, Startrak and Mill Mountain, dominate the Columbus market. Startrak has developed three new marketing strategies, 1, 2, and 3, for the fall season, which include various...
-
Bernices Pizza Restaurant opened the previous year, and in addition to sit-down restaurant service they filled take-out orders (picked up by customers) and some delivery orders using the owners car....
-
Record the following details relating to a carpet retailer for the month of November 2017 and extract a trial balance as at 30 November 2017. 2017 Nov 1 Started in business with 15,000 in the bank. 3...
-
You are to enter up the necessary accounts for the month of October from the following information relating to a small printing firm. Then balance-off the accounts and extract a trial balance as at...
-
On 1 October 2016, the owner of the USS Enterprise, Mr Kirk, decides that he will boldly go and keep his records on a double entry system. His assets and liabilities at that date were: Kirk's...
Study smarter with the SolutionInn App