Question: A project consists of five activities Optimistic Most Probable Pessimistic Activity Predecessor Time (hr) Time (hr) Time (hr) Floor sanding - 3 4 5 Floor
A project consists of five activities
|
|
| Optimistic | Most Probable | Pessimistic |
| Activity | Predecessor | Time (hr) | Time (hr) | Time (hr) |
| Floor sanding | - | 3 | 4 | 5 |
| Floor buffing | FL sanding | 1 | 2 | 3 |
| Paint Ceiling | ||||
| Paint mixing | - | 0.5 | 1 | 1.5 |
| Paint Wall | Paint Mix | 1 | 2 | 9 |
| Paint Ceiling | Paint Mix | 1 | 5.5 | 7 |
What is the Std Deviation of the Critical Path?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
