Question: A project consists of seven activities whose time estimates are given in the table below: Activity Estimated Duration (in days) - Optimistic Most Likely Pessimistic
A project consists of seven activities whose time estimates are given in the table below:
Activity Estimated Duration (in days)
- Optimistic Most Likely Pessimistic
1-2 4 10 16
1-3 3 6 9
1-4 4 7 16
2-5 5 5 5
3-5 8 11 32
4-6 4 10 16
5-6 2 5 8
a) Find the critical path of the project
b) Calculate the planned duration of the project.