Question: A project consists of seven activities whose time estimates are given in the table below: Activity Estimated Duration (in days) - Optimistic Most Likely Pessimistic

A project consists of seven activities whose time estimates are given in the table below:

Activity Estimated Duration (in days)

- Optimistic Most Likely Pessimistic

1-2 4 10 16

1-3 3 6 9

1-4 4 7 16

2-5 5 5 5

3-5 8 11 32

4-6 4 10 16

5-6 2 5 8

a) Find the critical path of the project

b) Calculate the planned duration of the project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!